U.S. General Services Administration





    Administrator's Semiannual 
Management Report to Congress









Report No.57
April 1, 2017 - September 30, 2017


U.S. General Services Administration
Timothy O. Horne
Acting Administrator

Office of Administrative Services 
Cynthia A. Metzler
Chief Administrative Services Officer

Office of Executive Secretariat and Audit Management 
Theresa Ottery
Director

October 2017

This report is in the public domain.	Authorization to reproduce it in whole or in part is 
granted. While permission to reprint this publication is not necessary, the citation should be:
U.S. General Services Administration, Office of Administrative Services, GAO/IG Audit 
Management Division, Administrator's Semiannual Management Report to the Congress, No. 
57, Washington, DC 20405.

Copies of this report can be obtained using any of the following:

Mail:	Office of Administrative Services, Office of Executive Secretariat and Audit 
Management
U.S. General Services Administration 
1800 F Street, NW
Washington, DC 20405

E-mail: GAO-IGAuditMgmtDiv@gsa.gov 
Online: Semiannual Report to Congress 
Telephone: (202) 501-1795


Contents
Synopsis of Audit Activity	4
Overview	5
U.S. General Services Administration Organization	5
Organization of Audit Follow-up Program	6
Agency Audit Follow-up Official	6
The Chief Administrative Services Officer (CASO)	6
Heads of Services and Staff Offices	6
Audits with Disallowed Costs	7
Audits with Better Use Funds (Potential Cost Savings)	8
Audits under Appeal/Litigation	9
Contract Audits	10
Internal Audits	18
Open OIG Recommendations Not Fully Resolved as of September 30, 2017	19
Glossary of Terms	30
Appendix	32


Synopsis of Audit Activity

The Inspector General Act of 1978, as amended, requires the Administrator of General 
Services to report directly to Congress on management decisions and final actions taken 
on audit recommendations made by the Office of Inspector General (OIG) of the General 
Services Administration (GSA).

This report covers the period of April 1, 2017, through September 30, 2017. Included in 
the report are summaries of GSA audit activities concerning the following:

-	GSA implementation of OIG audit report recommendations.
-	Final actions not taken on audits 1 year after the date of the management 
decision.
-	Audit reports and audit actions involving financial recommendations, including 
disallowed costs, funds to be put to better use (better use funds), or both.

On April 1, 2017, GSA had 132 contract and internal audit reports pending final action. 
These reports contained financial recommendations totaling $1,687,881,808.

-	Financial recommendations for 113 contract audits totaled $1,687,881,808.
-	Financial recommendations for 19 internal audits with no monetary returns.

Between April 1, 2017, and September 30, 2017, GSA finalized management decisions 
on 33 audit reports concerning nationwide GSA programs and operations.

-	A total of $1,579,886 in pre-award contracts, post-award contracts, and internal 
program spending was found to have been incorrectly charged to the 
Government and determined to be disallowed costs in 24 of the 33 audits.
-	In 23 of the 33 audits, the OIG recommended that $108,031,741 could be used 
more effectively (better use funds) if management took action to implement and 
complete the OIG recommendations.1

During this 6-month reporting period, GSA successfully took final action on 43 audits. 
These audits represent the potential recovery of $63,724,876 in Government funds and 
the identification of $909,472,406 in potential future savings.

As of September 30, 2017, GSA had 122 open audit reports. Three of these audits involve 
claims under appeal or in litigation.












1 The Appendix on page 32 reflects audits completed by the GSA-OIG Office of Audits. The above count reflects audits completed by the 
GSA-OIG Office of Audits and the GSA-OIG Office of Inspections.


Overview

This report, GSA's 57th report to Congress since the implementation of the reporting 
requirement, presents management's perspective on audit resolution and follow-up 
activity for the semiannual reporting period, in addition to general statistical summaries. 
The data in the report indicates that GSA's audit monitoring and management activities 
continue to play a significant role in the efficient management of GSA operations, the 
accomplishment of the agency mission, and the effective use of taxpayer dollars.

U.S. General Services Administration Organization

GSA's Public Buildings Service and Federal Acquisition Service provide government- 
wide delivery of real estate, acquisition, and technology services, while GSA's Office of 
Government-wide Policy manages the development of certain government-wide policies 
and regulations, as well as those for GSA only. GSA's 11 regions provide local support 
to Federal agencies nationwide, while GSA's several staff offices provide support to 
other GSA organizations and to other Federal agencies and the public.

The Administrator of GSA directs the execution of all GSA functions. Members of the 
Administrator's office, as well as Heads of Services and Staff Offices, advise and make 
recommendations on policy or operational issues of national scope. They are also 
responsible for execution of programs and services within their service, or staff office, 
under the leadership of the Administrator.


Organization of Audit Follow-Up Program

GSA has effective systems in place for tracking and managing audit recommendations. 
In addition, GSA's senior management is committed to ensuring that appropriate 
corrective action is taken.	Agency managers have the responsibility to act on the 
auditor's recommendations, with the audit resolution process being supervised by the 
agency's audit follow-up official.	A description of the responsibilities of GSA officials 
involved in the audit follow-up process is set forth below:

Agency Audit Follow-up Official

The Deputy Administrator is the Agency Audit Follow-up Official responsible for the audit 
follow-up program.	This position has overall responsibility for ensuring the adequacy of 
the agency's audit follow-up program, monitoring the resolution of audit 
recommendations, and ensuring the prompt implementation of corrective actions. This 
position also makes final decisions to resolve differences between agency management 
and the OIG.

The Chief Administrative Services Officer (CASO)

The CASO provides direction and oversight to the officials in the Office of Administrative 
Services (OAS) who manage the GSA's Audit Resolution and Follow-up System. Their 
responsibilities include:

-	Acting as the liaison with the Government Accountability Office (GAO) for the 
coordination of GAO audits in progress within GSA and for preparation of 
responses and reports for the signature of the Administrator on GAO 
recommendations as required by law;
-	Ensuring timely resolution and implementation of internal and external audit 
recommendations made by the GAO and the OIG;
-	Overseeing the collection and proper accounting of monetary amounts determined 
due to the Government as the result of audit-related claims;
-	Analyzing GSA's programs, upon request from the Administrator, particularly as 
related to past or present audit recommendations; and,
-	Maintaining an automated report control system for both internal and external 
audits that provides an accurate means for tracking and documenting actions 
taken to implement audit recommendations.

Heads of Services and Staff Offices

Heads of Services and Staff Offices, to whom audit recommendations pertain, have 
primary responsibility for resolving and implementing recommendations promptly. 
Their responsibilities include:

-	Ensuring controls are implemented to provide timely, accurate, and complete 
responses to audit reports;
-	Developing, advocating, and documenting agency positions on audit 
recommendations;
-	Preparing responses for GAO draft reports and transmittals for final GAO reports 
in coordination with OAS;
-	Providing comments on audit decision papers prepared by the OIG to ensure that 
management's position on unresolved audit recommendations is properly stated.




Final action for the six-month period 
Ending SEPTEMBER 30, 2017

A.	Audit reports for which final action had 
not been taken by the commencement of 
the reporting period.

B.	Audit reports on which GSA/OIG 
management decisions were made during 
the reporting period.
Number of Audit 
Reports

132


33
Disallowed 
Costs

$115,961,282



$	1,579,886
C.	Audit reports on which final action was 
taken during the reporting period.
(i)	the dollar value of disallowed costs
-	collections	$19,761,118
- offset	$1,574,737
-	property in lieu of cash...	$0
- surplus	$1,198,340
-	other ..............................	$0
(ii) the dollar value of disallowed costs 
that were written off by management.
43
$ 63,724,876

$ 22,534,195






$ 41,190,681
D.	Audit reports for which no final action
122
$ 57,412,203
has been taken by the end of the reporting


period and audit reports issued during this


reporting period.





 Final action for the six-month	Number of Audit 
Ending SEPTEMBER 30, 2017		Reports
A.	Audit reports for which final	132
action had not been taken by the 
commencement of the reporting 
period.
B.	Audit reports on which	33
management decisions were 
made during the reporting period.
  No budget Impact 
(Actual and Estimated)
$1,571,920,526



$108,031,741
Budget 
Impact
$0



$0
C.	Audit reports on which final
43
$909,472,406
$0
action was taken during the



reporting period.



(i) the actual dollar value of

$0

recommendations that were



actually completed.



(ii) the actual dollar value of

$0

recommendations that



management has subsequently



concluded should not or could not



be implemented or completed.



(iii) the actual dollar value of

$0

recommendations that



management has subsequently



concluded should not or could not



be determined (calculated).



(iv) the estimated dollar value of

$909,472,406

''funds to be put to better use'' as



agreed to by GSA management



and the OIG.



D.	Audit reports for which no
122
$716,561,750
$0
final action has been taken by



the end of the reporting period



and audit reports issued during



this reporting period.





Audits under Appeal/Litigation



   REPORT NUMBER 
NAME OF CONTRACTOR

DATE OF 
REPORT
MANAGEMENT DECISION 
AMOUNTS


Disallowed Costs
A140110P4X15003

Suffolk Construction Company, Inc.

11/10/2014

$0
A140116P4X15016

City Lights Electrical Company, Inc.

01/30/2015

$0
A140118P4X16005

N.B. Kenney Company, Inc.

11/13/2015

$0





REPORT 
NUMBER NAME 
OF 
CONTRACTOR

DATE OF 
REPORT
MANAGEMENT DECISION 
AMOUNTS

REASON FOR 
NO
FINAL ACTION


Disallowed 
Costs
Better Use 
Funds


A090042Q9X09019
Postaward Audit Report on 
Direct Costs Incurred on 
Trilogy Project: Computer 
Sciences Corporation, 
Contract Number GS00- 
T99-ALD204



12/29/2008



$14,951,923

Investigation in 
process - An 
investigation has 
been opened by 
either the OIG or 
the Justice 
Department 
regarding actions 
taken by the
contractor


A110088Q3X11079
Global Protection USA, Inc.


07/28/2011


$29,337

In negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A100119Q6X11081
Noble Sales Co., Inc.



08/03/2011



$0

Price/settlement 
negotiated - 
Negotiations 
have been 
completed 
between 
Contracting 
Officer and
contractor

A110209Q6X12057
Propper 
International Sales, 
Inc.


08/15/2012


$2,063,375

In negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A120071Q2X13002
ICF Z-Tech, Inc.


10/16/2012


$14,580

In negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A130071Q5X14018
Industries for the Blind, Inc.


01/31/2014


$306,596

In negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor




REPORT 
NUMBER NAME 
OF 
CONTRACTOR

DATE OF 
REPORT
MANAGEMENT DECISION 
AMOUNTS

REASON FOR 
NO
FINAL ACTION


Disallowed 
Costs
Better Use 
Funds



A130099P4X14011
HCBeck, Ltd.


03/24/2014


$0

In negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A130049Q4X14024
SimplexGrinnell LP


03/31/2014


$0

In negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor

A130136Q3X14026
Fisher Scientific 
Company LLC


04/14/2014


$0

In negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor



A110139Q9X14028
Alaska 
Structures, 
Incorporated




04/24/2014




$1,999,255

Investigation in 
process - An 
investigation has 
been opened by 
either the OIG or 
the Justice 
Department 
regarding actions 
taken by the 
contractor


A140057Q3X14043
ATD-American Company


06/19/2014


$4,895

In negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A130043Q2X14049
ICF Z-Tech, Inc.


07/16/2014


$2,482,454

In negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor





REPORT 
NUMBER NAME 
OF 
CONTRACTOR

DATE OF 
REPORT
MANAGEMENT DECISION 
AMOUNTS

REASON FOR 
NO
FINAL ACTION


Disallowed 
Costs
Better Use 
Funds



A130116Q3X14053
Management 
Concepts, Inc.



07/29/2014



$14,121

In the process of 
collection - GSA is 
in the process of 
collecting funds 
owed the 
government from 
the contractor


A140132Q7X14061
A-T Solutions, Inc.


09/16/2014


$239,961

In negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor



A140110P4X15003
Suffolk 
Construction 
Company, Inc.




11/10/2014




$0

Litigation in 
process - The 
contractor has 
appealed the 
Contracting 
Officer's decision 
and the audit is 
now in the litigation
process



A140116P4X15016
City Lights 
Electrical 
Company, Inc.




01/30/2015




$0

Litigation in 
process - The 
contractor has 
appealed the 
Contracting 
Officer's decision 
and the audit is 
now in the litigation 
process


A140149P4X15027
Donaldson Interiors, Inc.


03/27/2015


$0

In negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor

A140039Q4X15029
High Performance 
Technologies 
Innovations, LLC


03/31/2015


$539,872

In negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor





REPORT 
NUMBER NAME 
OF 
CONTRACTOR

DATE OF 
REPORT
MANAGEMENT DECISION 
AMOUNTS

REASON FOR 
NO
FINAL ACTION


Disallowed 
Costs
Better Use 
Funds



A140074Q6X15037 
TASC, Inc.


06/10/2015


$1,886,901

In negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A150071Q7X1504 
CAS, Inc.


07/08/2015


$21,171

In negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A140079Q6X15061 
CACI, INC. - 
FEDERAL


09/23/2015


$0

In negotiation - 
Negotiations are 
proceeding 
between
Contracting Officer 
and contractor

A150002Q3X15063
Government 
Contract Solutions, 
Inc.


09/30/2015


$70,640

In negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A150083QAX16004
LCG Systems, LLC



11/10/2015



$149,663

Price/settlement 
negotiated - 
Negotiations have 
been completed 
between 
Contracting Officer


A150077QAX16006
Office Depot, Inc.


11/12/2015


$0

In negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor





REPORT 
NUMBER NAME 
OF 
CONTRACTOR

DATE OF 
REPORT
MANAGEMENT DECISION 
AMOUNTS

REASON FOR 
NO
FINAL ACTION


Disallowed 
Costs
Better Use 
Funds




A140118P4X16005
 N.B. Kenney 
Company, Inc.




11/13/2015




$0

Litigation in 
process - The 
contractor has 
appealed the 
Contracting 
Officer's decision 
and the audit is 
now in the litigation
process

A140064Q3X16007
AllWorld 
Language 
Consultants, Inc.


11/18/2015


$35,292

In negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor

A150113P4X16008
Matsuo Engineering 
Centerre Construction, 
A Joint Venture


11/20/2015


$0

In negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A150069Q5X16012
Research Triangle Institute


12/03/2015


$61,375

In negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor

A090175Q4X16011
Square One Armoring 
Services


12/03/2015


$0

In negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer
and contractor


A140055Q2X1601 
SRC, Inc.


12/07/2015


$637,423

In negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor





REPORT 
NUMBER NAME 
OF 
CONTRACTOR

DATE OF 
REPORT
MANAGEMENT DECISION 
AMOUNTS

REASON FOR 
NO
FINAL ACTION


Disallowed 
Costs
Better Use 
Funds



A150142Q7X16015
IDSC Holdings, LLC



12/14/2015



$36,620

Price/settlement 
negotiated - 
Negotiations 
have been 
completed 
between 
Contracting 
Officer and
contractor

A140146P4X16017
Cauldwell Wingate 
Company, LLC


12/21/2015


$0

In negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A140145P4X16018
Pace Plumbing Corporation


12/28/2015


$0

In negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor

A140148P4X16022
Five Star 
Electric 
Corporation


01/29/2016


$0

In negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A150104Q7X16026
Kipper Tool Company


02/23/2016


$57,177

In negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor

A150093Q3X16027
Innovative Management 
& Technology 
Approaches, Inc.


03/02/2016


$143,095

In negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor





REPORT 
NUMBER NAME 
OF 
CONTRACTOR

DATE OF 
REPORT
MANAGEMENT DECISION 
AMOUNTS

REASON FOR 
NO
FINAL ACTION


Disallowed 
Costs
Better Use 
Funds


A140147P2X16030
ASM Mechanical 
Systems, Inc.


03/30/2016


$1,120,928

In negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A150097Q9X16033
Acumen, LLC


04/18/2016


$0

In negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor

A160029QAX16036
Delta Research 
Associates, Inc.


04/26/2016


$112,884

In negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor

A150095Q3X16037
DRS Technical 
Services, Inc.


04/27/2016


$0

In negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A160026Q7X16039
Skyline Unlimited, Inc.


05/12/2016


$35,373

In negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor

A150073Q2X16040
Simmonds 
Precision 
Products, Inc.


05/23/2016


$531

In negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor





REPORT 
NUMBER NAME 
OF 
CONTRACTOR

DATE OF 
REPORT
MANAGEMENT DECISION 
AMOUNTS

REASON FOR 
NO
FINAL ACTION


Disallowed 
Costs
Better Use 
Funds


A150085Q9X16043
Mathematica Policy 
Research, Inc.


06/24/2016


$172,827

In negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A150068Q4X16045
COLSA Corporation



06/30/2016



$0

Price/settlement 
negotiated - 
Negotiations have 
been completed 
between 
Contracting Officer


A150107Q6X16056
    Radiance 
Technologies, Inc.



08/04/2016



$529,097

Unresolved - 
Agreement has not 
been reached 
between OIG and 
Contracting Officer 
on the Decision 
Record

A160093Q7X16074
United Liquid Gas 
Company


09/19/2016


$3,321,947

In negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


Financial recommendations are not included for internal audits or actions that are not completed.



REPORT NUMBER 
TITLE OF REPORT

DATE OF 
REPORT
MANAGEMENT DECISION 
AMOUNTS

REASON FOR NO 
FINAL ACTION

PROJECTED 
COMPLETION 
DATE


Disallowed 
Costs
Better Use 
Funds


A140008Q9P15002
FAS Needs to 
Strengthen its Training 
and Warranting 
Program for 
Contracting Officers


06/26/2015


$0



Audit is in the 
Implementation 
Stage


06/25/2018
A150033Q9P16002
The Federal Acquisition 
Service Needs a 
Comprehensive Human 
Capital Plan for its 
Contract Specialist 
Workforce


07/22/2016


$0



Audit is in the 
Implementation 
Stage


10/31/2017
A120026Q6P16003
IT Reseller Contracts 
Present Significant 
Challenges for GSA's 
Schedules Program

07/22/2016

$0


Audit is in the 
Implementation 
Stage

12/04/2017
A150009P5R16003
PBS Energy Savings 
Performance Contract 
Awards May Not Meet 
Savings Goals

09/27/2016

$0


Audit is in the 
Working Stage

TBD after 
negotiations 
are completed



Number and 
Title of Report
  Report 
Issue Date
Recommendation 
Number
     Entire 
Recommendation
 Original 
Due Date
Current Due 
Date



A140008Q9P15002
FAS Needs to Strengthen 
its Training and 
Warranting Program for 
Contracting Officers





06/26/2015





004

Grant Central Office 
portfolio training 
coordinators system 
access to generate 
reports in the Federal 
Acquisition Institute 
Training Application 
System that track 
Federal Acquisition 
Certification in 
Contracting and warrant 
compliance for their 
assigned staff.





06/15/2016





06/25/2018

A150033Q9P16002
 The Federal Acquisition 
Service Needs a 
Comprehensive Human 
Capital Plan for its 
Contract Specialist 
Workforce.


07/22/2016


002

Evaluate and update the 
comprehensive human 
capital plan on an annual 
basis.


10/31/2017


10/31/2017






A120026Q6P16003
IT Reseller Contracts 
Present Significant 
Challenges for GSA's 
Schedules Program








07/22/2016








003A

Improve price protection 
for IT schedule reseller 
contracts by: (a) 
Establishing controls to 
ensure that contracting 
officers obtain accurate, 
current, and complete 
manufacturer commercial 
sales practices 
information for offered 
items when the resellers 
have low or no 
commercial sales. The 
controls should ensure 
that the specific items 
involved are not awarded 
until commercial sales 
practices information is 
provided.








03/31/2017








12/04/2017


A120026Q6P16003
IT Reseller Contracts 
Present Significant 
Challenges for GSA's 
Schedules Program




07/22/2016




003B

Improve price protection 
for IT schedule reseller 
contracts by establishing 
controls to ensure that 
deviations to the Price 
Reductions clause do not 
diminish price protections 
and are properly 
approved by the Head of 
the Contracting Activity.



03/31/2017



12/04/2017




Number and 
Title of Report
  Report 
Issue Date
Recommendation 
Number
      Entire 
Recommendation
 Original 
Due Date
Current Due 
Date


A120026Q6P16003
IT Reseller Contracts 
Present Significant 
Challenges for GSA's 
Schedules Program




07/22/2016




004

Cancel IT schedule 
reseller contracts that do 
not meet the $25,000 
minimum sales 
requirement of the 
Schedules Program, 
focusing initially on those 
with no sales; or 
document the contract 
files to support decisions 
to maintain the contracts.




01/10/2017




12/04/2017

A120026Q6P16003
IT Reseller Contracts 
Present Significant 
Challenges for GSA's 
Schedules Program



07/22/2016



005

Consider increasing the
$25,000 minimum sales 
threshold for IT schedule 
reseller contracts to a 
level that offsets the 
government's cost to 
award and administer a 
schedule contract.



01/10/2017



12/04/2017

A120026Q6P16003
IT Reseller Contracts 
Present Significant 
Challenges for GSA's 
Schedules Program


07/22/2016


006

Consider alternatives to 
the current $2,500 
minimum payment 
clause in IT schedule 
reseller contracts.


03/31/2017


12/04/2017

A150009P5R16003
PBS Energy Savings 
Performance Contract 
Awards May Not Meet 
Savings Goals.

09/27/2016

001
 Witness and 
independently verify 
baselines developed by 
the energy company.








GSA is awaiting approval 
from OIG on the submitted 
response package.

A150009P5R16003
PBS Energy Savings 
Performance Contract 
Awards May Not Meet 
Savings Goals.


09/27/2016


001b

Document their 
witnessing of the energy 
company's on-site 
baseline measurements.


A150009P5R16003
PBS Energy Savings 
Performance Contract 
Awards May Not Meet 
Savings Goals.


09/27/2016


002

Ensure all 
components of the
energy-related savings 
calculations, including 
O&M savings, are 
accurate and can be 
reconciled to the task 
order schedules.





Number and 
Title of Report
  Report 
Issue Date
Recommendation 
Number
     Entire 
Recommendation
 Original 
Due Date
Current Due 
Date

A150009P5R16003
PBS Energy Savings 
Performance Contract 
Awards May Not Meet 
Savings Goals.


09/27/2016


002b

Renegotiate O&M 
contracts to achieve the 
estimated savings on 
existing ESPCs with 
O&M savings.





















GSA is awaiting approval 
from OIG on the submitted 
response package.

A150009P5R16003
PBS Energy Savings 
Performance Contract 
Awards May Not Meet 
Savings Goals.


09/27/2016


002c

Develop and implement 
policy and procedures to 
confirm savings from 
GSA-managed O&M 
contracts are achievable 
at time of award for 
future ESPCs.



A150009P5R16003
PBS Energy Savings 
Performance Contract 
Awards May Not Meet 
Savings Goals.




09/27/2016




003

Implement training on 
price reasonableness 
determinations for ESPC 
contracting, including the 
development and use of 
independent government 
estimates, to improve 
compliance with 
regulations and 
guidance.


A150009P5R16003
PBS Energy Savings 
Performance Contract 
Awards May Not Meet 
Savings Goals.


09/27/2016


004

Align each ESPC task 
order term with the PBS 
Portfolio Strategy holding 
period for the asset.



A150009P5R16003
PBS Energy Savings 
Performance Contract 
Awards May Not Meet 
Savings Goals.




09/27/2016




005

Require written 
justifications for not using 
the DOE super ESPC if 
GSA awards stand-alone 
ESPCs in the future. The 
ESPC Program 
Management Office 
should review and 
approve all such 
justifications.


A150009P5R16003
PBS Energy Savings 
Performance Contract 
Awards May Not Meet 
Savings Goals.


09/27/2016


005b

Ensure future ESPCs 
comply with competition 
requirements for added 
O&M services or receive 
management approval 
for non-competitive 
procedures.





Number and 
Title of Report
  Report 
Issue Date
Recommendation 
Number
      Entire 
Recommendation
 Original 
Due Date
Current Due 
Date

A150009P5R16003
PBS Energy Savings 
Performance Contract 
Awards May Not Meet 
Savings Goals.


09/27/2016


005c

Ensure acquisition plans 
for future stand-alone 
ESPCs are reviewed by 
the Head of Contracting 
Activity.





GSA is awaiting approval 
from OIG on the submitted 
response package.

A150009P5R16003
PBS Energy Savings 
Performance Contract 
Awards May Not Meet 
Savings Goals.


09/27/2016


006

Require solicitations for 
future stand-alone 
ESPCs to state that 
Measurement and 
Verification Plans must 
be approved prior to 
contract award.



JE17-001
Evaluation of 18F


10/24/2016


006

Establish reliable internal 
controls to ensure that 
18F's future billings are 
accurate.


09/29/2017


09/29/2017


JE17-001
Evaluation of 18F


10/24/2016


007

Ensure that 18F's billing 
records are retained in 
accordance with GSA 
records management 
standards.


10/13/2017


10/13/2017




Number and 
Title of Report
  Report 
Issue Date
Recommendation 
Number
      Entire 
Recommendation
 Original 
Due Date
Current Due 
Date











A150132P4R17001
GSA's Decisions to 
Vacate and Renovate the 
Leased Federal 
Courthouse in Pensacola 
Are Based on Faulty 
Premises.













10/25/2016













001

Reanalyze options for 
housing the tenants of 
the 1 North Palafox 
Street courthouse. As 
part of this analysis, PBS 
should: Ensure a 
comparison of equivalent 
options is reflected; 
Ensure the designs for 
the renovation, new, and 
leased construction 
options meet current 
building standards; 
Ensure the designs for 
the new and leased 
construction options 
comply with the U.S. 
Courts Design Guide; 
Ensure the estimated 
reversion values of the 
new and leased 
courthouse options are 
developed by an 
independent appraiser;
ensure lease-buyout and 
other potential settlement 
costs are incorporated; 
and Develop and 
incorporate project 
schedules into the 
financial analysis that are 
based on historical 
performance of projects 
with similar scope or 
scale.


















GSA and OIG are still 
negotiating on 
implementation efforts.


A150132P4R17001
GSA's Decisions to 
Vacate and Renovate the 
Leased Federal 
Courthouse in Pensacola 
Are Based on Faulty 
Premises.




10/25/2016




002

Suspend all contracts 
and procurements for the 
prospectus project until 
PBS secures ownership 
of the 1 North Palafox 
Street courthouse, if 
PBS's revised analysis 
demonstrates that 
ownership is in the best 
interest of the 
government.





Number and 
Title of Report
  Report 
Issue Date
Recommendation 
Number
      Entire 
Recommendation
 Original 
Due Date
Current Due 
Date

A150132P4R17001
GSA's Decisions to 
Vacate and Renovate the 
Leased Federal 
Courthouse in Pensacola 
Are Based on Faulty 
Premises.


10/25/2016


003

Develop and implement 
a solution to address the 
tenants' security, privacy, 
and storage concerns at 
the 25 West Government 
Street leased space.







GSA and OIG are still 
negotiating on 
implementation efforts.

A150132P4R17001
GSA's Decisions to 
Vacate and Renovate the 
Leased Federal 
Courthouse in Pensacola 
Are Based on Faulty 
Premises.



10/25/2016



004

Implement an interim 
solution to address 
security, water intrusion, 
and mold issues, as well 
as sanitary conditions; at 
the 1 North Palafox 
Street courthouse.


A130003P2R17002
Procurement and Internal 
Control Issues Exist 
within PBS's 
Brooklyn/Queens/Long 
Island Service Center



01/20/2017



006

Determine the corrective 
actions needed to 
remediate the missing 
and incorrect documents 
that were identified by 
the audit team's review 
of the contract files.



09/11/2017



11/10/2017


A160037Q3P17001
Audit of Price Evaluations 
and Negotiations for the 
Professional Services 
Schedule Contracts




03/21/2017




001

Direct the Office of 
Professional Services 
and Human Capital 
Categories to perform a 
formal price analysis on 
PSS migrated contracts 
to determine if the 
contract pricing is fair 
and reasonable.



07/31/2017



07/31/2017



A160037Q3P17001
Audit of Price Evaluations 
and Negotiations for the 
Professional Services 
Schedule Contracts





03/21/2017





002

Direct the Office of 
Professional Services 
and Human Capital 
Categories to 
discontinue the use of 
the "Pre and Price 
Negotiation 
Memorandum" template 
and use the separate 
Pre-Negotiation 
Memorandum and Price 
Negotiation 
Memorandum mandated 
by FAS Instructional 
Letter 2011-02.




07/31/2017




07/31/2017




Number and 
Title of Report
  Report 
Issue Date
Recommendation 
Number
      Entire 
Recommendation
 Original 
Due Date
Current Due 
Date



A160037Q3P17001
Audit of Price Evaluations 
and Negotiations for the 
Professional Services 
Schedule Contracts





03/21/2017





003

Develop and issue 
guidance to contracting 
staff on documenting 
detailed price analyses, 
including reviews of 
comparable labor 
categories and rates, in 
order to support 
contracting actions in the 
contract file.





12/29/2017





12/29/2017









A160024PRR17004
Audit of PBS's Planning 
and Funding for 
Exchange Projects











03/30/2017











001

Update exchange 
guidance to:
a.	Require financial and 
business case analyses 
that fully quantify risk 
for all potential 
exchanges
when making the 
decision to exchange, 
dispose of, or retain a 
property. If an 
exchange is pursued, 
require that PBS 
continue to quantify risk 
throughout the project;
b.	Address funding for 
change orders, support 
costs, and funding 
shortages; as well as 
the use of cash 
equalization; and
c.	Require PBS to 
estimate support costs 
and identify funding 
sources when planning 
an exchange.











09/29/2017











12/29/2017

A170016P6R17005
The Robert A. Young 
Federal Building Needs 
Vehicle Collision 
Prevention Controls



05/10/2017



001

Immediately install 
barriers or other vehicle 
collision prevention 
controls on the RAY 
building's north side and 
northeast corner.





GSA is awaiting approval 
from OIG on the submitted 
response package.

A170016P6R17005
The Robert A. Young 
Federal Building Needs 
Vehicle Collision 
Prevention Controls


05/10/2017


002

Assess the overall 
building site to ensure 
that it is adequately 
protected from vehicular 
threats.





Number and 
Title of Report
  Report 
Issue Date
Recommendation 
Number
      Entire 
Recommendation
 Original 
Due Date
Current Due 
Date



A160118Q3P17003
GSA Lacks Controls to 
Effectively Administer the 
Computers for Learning 
Website




07/13/2017




001

Design and implement 
controls that prevent 
ineligible organizations 
from being granted 
access to GSA's CFL 
website and receiving 
donated IT equipment 
intended for eligible 
schools and educational 
nonprofit organizations.








GSA is awaiting approval 
from OIG on the submitted 
response package.


A160118Q3P17003
GSA Lacks Controls to 
Effectively Administer the 
Computers for Learning 
Website



07/13/2017



002

Establish a requirement 
that federal agencies be 
informed of their 
responsibility to validate 
an organization's 
eligibility prior to making 
donations using GSA's 
CFL website.


A160112OTF17002
Limited Scope Audit of 
the System Security 
Controls for Enterprise 
Acquisition System 
Integrated (EASi)



08/09/2017



001

Ensure that the security 
control weaknesses 
identified in our audit are 
mitigated in accordance 
with applicable 
standards, guidelines, 
and recommendations 
established by NIST and 
CIS.








GSA is awaiting approval 
from OIG on the submitted 
response package.

A160112OTF17002
Limited Scope Audit of 
the System Security 
Controls for Enterprise 
Acquisition System 
Integrated (EASi)



08/09/2017



002

Review and apply GSA's 
IT baseline security 
hardening requirements 
to EASi's server 
operating systems, web 
application, and 
database.


A150009P5R17006
PBS National Capital 
Region's $1.2 Billion 
Energy Savings 
Performance Contract for 
White Oak was Not 
Awarded or Modified in 
Accordance with 
Regulations and Policy




08/24/2017




001

Take immediate action to 
expedite the 
procurement of a new 
O&M contract that 
adheres to competition 
requirements specified in 
the Competition in 
Contracting Act of 1984 
and the Federal 
Acquisition Regulation.



GSA is developing its 
response package for 
submission to OIG.




Number and 
Title of Report
  Report 
Issue Date
Recommendation 
Number
      Entire 
Recommendation
 Original 
Due Date
Current Due 
Date

A150009P5R17006
PBS National Capital 
Region's $1.2 Billion 
Energy Savings 
Performance Contract for 
White Oak was Not 
Awarded or Modified in 
Accordance with 
Regulations and Policy



08/24/2017



002

Determine and 
implement the 
appropriate corrective 
action needed for PBS 
NCR personnel's
non-compliance with 
competition 
requirements.























GSA is developing its 
response package for 
submission to OIG.

A150009P5R17006
PBS National Capital 
Region's $1.2 Billion 
Energy Savings 
Performance Contract for 
White Oak was Not 
Awarded or Modified in 
Accordance with 
Regulations and Policy



08/24/2017



003

Institute the necessary 
management controls to 
ensure that 
procurements for the 
campus comply with the 
Competition in 
Contracting Act of 1984 
and Federal Acquisition 
Regulation 6.3.

A150009P5R17006
PBS National Capital 
Region's $1.2 Billion 
Energy Savings 
Performance Contract for 
White Oak was Not 
Awarded or Modified in 
Accordance with 
Regulations and Policy




08/24/2017




004A
Implement internal 
controls to ensure 
ESPCs comply with DOE 
regulations and guidance 
including verifying
that costs of 
implementing energy 
conservation measures 
are paid for from the 
resulting cost savings.

A150009P5R17006
PBS National Capital 
Region's $1.2 Billion 
Energy Savings 
Performance Contract for 
White Oak was Not 
Awarded or Modified in 
Accordance with 
Regulations and Policy




08/24/2017




004B
Implement internal 
controls to ensure 
ESPCs comply with DOE 
regulations and guidance 
including witnessing
and independently 
verifying that
baselines developed by 
the energy company are 
accurate.


A150009P5R17006
PBS National Capital 
Region's $1.2 Billion 
Energy Savings 
Performance Contract for 
White Oak was Not 
Awarded or Modified in 
Accordance with 
Regulations and Policy




08/24/2017




004C

Implement internal 
controls to ensure 
ESPCs comply with DOE 
regulations and guidance 
including
verifying that the financial 
Selection Memorandum 
from the energy 
company is certified as 
being the best value for 
the government.




Number and 
Title of Report
  Report 
Issue Date
Recommendation 
Number
      Entire 
Recommendation
 Original 
Due Date
Current Due 
Date

A150009P5R17006
PBS National Capital 
Region's $1.2 Billion 
Energy Savings 
Performance Contract for 
White Oak was Not 
Awarded or Modified in 
Accordance with 
Regulations and Policy



08/24/2017



005A


Implement training for 
PBS NCR personnel 
responsible for the 
preparation of acquisition 
plans.























GSA is developing its 
response package for 
submission to OIG.

A150009P5R17006
PBS National Capital 
Region's $1.2 Billion 
Energy Savings 
Performance Contract for 
White Oak was Not 
Awarded or Modified in 
Accordance with 
Regulations and Policy



08/24/2017



005B

Implement training for 
PBS NCR personnel 
responsible for price 
reasonableness 
determinations for ESPC 
contracting, including the 
development and use of 
independent government 
estimates.


A150009P5R17006
PBS National Capital 
Region's $1.2 Billion 
Energy Savings 
Performance Contract for 
White Oak was Not 
Awarded or Modified in 
Accordance with 
Regulations and Policy



08/24/2017



005C


Implement training for 
PBS NCR personnel 
responsible for Contract 
file documentation 
requirements.

A150009P5R17006
PBS National Capital 
Region's $1.2 Billion 
Energy Savings 
Performance Contract for 
White Oak was Not 
Awarded or Modified in 
Accordance with 
Regulations and Policy




08/24/2017




005D
Implement training for 
PBS NCR personnel 
responsible for 
Compliance with 
requirements to hold a 
Preaward Review Board 
review prior to award, or 
if waived, a Postaward 
Review Board review for 
applicable task orders.


A150009P5R17006
PBS National Capital 
Region's $1.2 Billion 
Energy Savings 
Performance Contract for 
White Oak was Not 
Awarded or Modified in 
Accordance with 
Regulations and Policy



08/24/2017



006

Once the procurement of 
a new O&M contract is 
secured, as stated in 
Finding 1, include the 
Limitation of Government 
Obligation clause on all 
non-ESPC O&M 
services.




Number
and Title of Report
  Report 
Issue Date
Recommendation 
Number
      Entire 
Recommendation
 Original 
Due Date
Current Due 
Date

A170025QTP17004
Audit of Limited Scope 
Audit of GSA's 
Centralized Household 
Goods Traffic 
Management Program 
Tariff and Tender of 
Service



09/28/2017



001


Delete the shuttle service 
exception.







GSA is developing its 
response package for 
submission to OIG.

A170025QTP17004
Audit of Limited Scope 
Audit of GSA's 
Centralized Household 
Goods Traffic 
Management Program 
Tariff and Tender of 
Service



09/28/2017



002

Determine if the tariff 
needs a new provision to 
address the use of a 
smaller truck.





The following definitions, based on the Inspector General Act Amendment of 1978, 
apply to terms used in this Semiannual Management Report:

Questioned Costs.	Costs questioned by the OIG as a result of:

*	an alleged violation of a provision of a law, regulation, contract, grant, 
cooperative agreement, or other agreement or document governing 
the expenditure of funds;

*	a finding that, at the time of an audit, such cost is not supported by adequate 
documentation;

*	a finding that the expenditure of funds for the intended purpose is 
unnecessary or unreasonable.

Disallowed Cost.	Questioned costs that GSA management in a management 
decision sustained or agreed should not be charged to the Government.

Recommendation that Funds be Put to Better Use.	A recommendation by the 
OIG that funds could be used more efficiently if management took action to 
implement and complete the recommendations, including:

*	reductions in outlays;

*	de-obligation of funds from programs or operations;

*	withdrawal of interest subsidy costs on loans or loan guarantees, insurance or 
bonds;

*	costs not incurred by implementing recommended improvements related to 
the operations of the establishment, a contractor or grantee;

*	avoidance of unnecessary expenditures noted in pre-award reviews of 
contract or grant agreements;

*	any other savings that are identified specifically.

Management Decision.	The evaluation by management of the findings and 
recommendations included in an audit report and the issuance of a final decision 
by management and concurrence by the OIG concerning its response to such 
findings and recommendations, including planned corrective actions to remedy 
weaknesses identified in the report.

Final Action.	The completions of all actions that GSA management concluded 
in its management decision were necessary with respect to the findings and 
recommendations included in the audit report. In the event that GSA concluded 
no action was necessary, final action occurred when the management decision 
was made.



Management Actions - Questioned Costs. The following is a list of the different 
management actions used by GSA management to resolve questioned costs in an 
audit report.

�	Audit reports on which management decisions were made during the 
period: Data pertaining to the number of audit reports on which 
management decisions were made during the period and the associated 
amount of disallowed costs was furnished by the OIG.

�	Write-offs: For the purposes of this report, write-offs are interpreted to 
represent the difference between the disallowed cost and the amount 
successfully recovered.

Management Actions - Better Use Funds.	The following is a list of the different 
management actions used by GSA management to resolve the "better use" of 
funds in an audit report.

*	Better Use Funds:	The figure represents amounts cited as "cost 
avoidance" and "funds to be put to better use," as agreed to by GSA 
management and the OIG. Prior to April 1990, no funds were identified by 
the OIG specifically as "funds to be put to better use," and no management 
decisions were issued based on the consideration of "better use" of funds.

*	Budget Impact Funds:	Funds identified as "budget impact" involve the 
obligation process. Audit-related savings of these funds, depending on 
the particular fund involved, may be available for reprogramming.

*	No Budget Impact Funds:	Funds identified as "no budget impact" are 
composed of estimated and actual amounts, and do not involve obligated 
monies, and, therefore, cannot be construed as having a material effect on 
GSA''s appropriated funds.

*	Audit reports on which management decisions were made during the 
period: Data pertaining to the number of audit reports on which 
management decisions were made during the period and the associated 
dollar amounts agreed to by management were furnished by the OIG.

*	Value of recommendations that management concluded should not or 
could not be calculable: Management was unable to determine the award 
amounts and "better use funds" implemented since the amount is included 
in the overall award to the prime contractor and savings could not be 
determined.


 
























This page is left blank intentionally.


 





U.S. General Services Administration
1800 F Street, NW 
Washington, DC 20405

www.gsa.gov